What projects are included in the $30.48 million Capital Improvement Project?

 

ADDITIONS

 
(4) classrooms $1,182,025
      Classroom FF&E allowance $48,000
Administrative office space $1,943,175
      Office FF&E allowance $150,000
Nurse's suite $267,750
Mechanical/circulation/miscellaneous $1,024,250
Electrical upgrades $$50,000
Kitchen additions $150,800
New kitchen equipment $250,000
Subtotal $5,066,000
   

RENOVATIONS

 
Auditorium improvements and upgrades  
Miscellaneous upgrades including seating, acoustics and lighting $1,772,000
Convert (2) toilet rooms $350,000

Music department upgrades
 
Renovate choral room $150,000
Renovate orchestra/band room $150,000
New SGI music room $60,000
New band/choral room office $30,000
New storage rooms $20,000
New corridor doors $5,000
New corridor and door $25,000
New HVAC system for music suite $200,000

Classroom renovations
 
Convert central admin offices to (2) special ed. classrooms $356,265
Convert (2) 1st floor offices into (1) classroom & convert 2nd floor office
and classroom into (2) classrooms
$108,900
      Classroom FF&E allowance  $60,000

Cafeteria and kitchen renovations
 
Miscellaneous renovations and upgrades including new wall partitions,
(5) pairs of doors, new ceilings, lighting, air handlers and air conditioning
$500,000
Kitchen renovations to improve layout and serving line $575,000
Relocate faculty lounge (displaced by new kitchen expansion) $112,250

Boys' locker room renovations
 
Renovate boys' locker room $250,000

STEAM Lab renovations
 
Steam Lab suite (converted from industrial & visual arts) $250,000
STEAM Lab equipment $250,000

BCS Improvements
 
Window replacement for original single pane windows $800,000
HVAC upgrades in old gym and library $430,000
New fire alarm system (required to meet current code) $450,000
Roof repairs $300,000
Corridor locker replacement $180,000
Classroom wall partition improvements $225,000
Subtotal $7,614,415
   

Site improvements

 
Athletic/physical education upgrades including multi-use artificial athletic field
with (8) lane track, 1,500 spectator bleachers, and field house with team
rooms, training room, storage rooms, restrooms and concession stand
$5,300,000
New parking lot and bus loop $1,200,000
Various site improvements including sidewalks, retaining walls, and sidewalk
from elementary school to new loop drive
$300,000
Subtotal $6,800,000
   

District-wide Infrastructure Improvements (Smart Schools Bond Act)

 
Upgrade wireless network and VOIP (Voice Over Internet Protocol) phone system $4,254,000
Subtotal $4,254,000 ($1.3 million is reimbursable through Smart Schools Bond Act)
   
Construction costs subtotal $23,734,415
10% contingency $2,373,441,50
Escalation (1.5 years at 3% per year $1,174,853.54
Total construction costs $27,282,710.04
Incidental Costs including land/property survey, insurance, construction manager, traffic study, legal fees, bond counsel, etc. $3,201,140.16
PROJECTED TOTAL BOND COST $30,483,850.21